Pilot plant for torrefaction & carbonisation

Continuous flow, torrefaction/ carbonization unit for the production of bio-coal/bio-char

Torrefaction pilot plant

Capacity 5 – 20 kg biomass/hour
Product 1 – 15 kg torrefied material/hour
Feedstock
Wood, straw, agricultural residues, pellets, etc.
Particle size up to 15 mm (after sizing)
Moisture content up to 20 wt% (after drying)
Typical runtime 1 – 6 hrs
Basic results bio-char samples, yield, overall mass & energy balance

Screening unit for torrefaction & carbonisation

Small scale screening unit for continuous flow, torrefaction & carbonization.

Torrefaction screening unit

Capacity 0.2 – 0.6 kg biomass/hour
Product 0.1 – 0.4 kg bio-char/hour
Feedstock
Wood, straw, agricultural residues, pellets, etc.
Particle size up to 10 mm (after sizing)
Moisture content up to 20 wt% (after drying)
Typical runtime 1 – 6 hrs
Basic results bio-char samples and overall yield